|
BRIGHAM BRIDGE PROGRESS | |||||||
|
Page last updated April 2003 | |||||||
|
Planning Permission for Brigham Bridge was Granted on 30th April 2001. Replacement bridge fitted 28th June 2002, completion of the bridge later this year. | |||||||
| Brigham Bridge was officially re-opened on the 5th April 2003 | |||||||
|
Brigham bridge open during the DNAA working party on 25th January, two of the first boats through the bridge. Soon this will be a reality to all the boats on the Navigation. | |||||||
|
|
||||||
|
Over the winter months DNAA members have had several
working parties at Brigham bridge. The bridge has been adjusted to
its working height, the track for the bridge running gear has been
fitted and work has commence painting the hand rails. Ground work
adjacent to the bridge has also been carried out; three retaining
walls and have been built. With the grant money now available work on
landscaping the area adjacent to the bridge and improvements to safety
(replacement of fencing) will be carried out by contractors before the
31st March 2003. | |||||||
|
The bearing has now been fitted along with 7 tons
of ballast weights. Simpson Civil Engineers have completed the concrete
work under the bridge and at the approaches to the bridge. The
bridge now requires adjusting to the correct level to mate up with
the road surfaces. This will entail packing up the bearing and
possible adjusting the weight of the ballast. D.N.A.A. members
have been working on the re-building of the retaining walls adjacent
to the bridge. One wall has been completed, work is in hand to
complete another retaining wall and bridge stop. Some repairs to
damaged brickwork are also required. Work has also commence by
D.N.A.A. members to paint the bridge hand rails white, completion of
the painting may be delayed due to weather conditions at present. | |||||||
|
Pictures of Brigham Bridge taken on Saturday 6th July Click
Here.
The bearing for the pintal is now available, once a time slot
convenient to all parties can be arranged the bearing will be
fitted. | |||||||
| |||||||
|
09th June 2002:Information Source, DNAA 7th June committee meeting, from the DNT Technical Committee Chairman Mr. Rodger Gooch. | |||||||
|
If all goes to plan the replacement of Brigham bridge should commence on 24th June. The work is planned to take 5 days for the removal of the present fixed bridge and the installation of a new swing bridge. Pictures of the removal and installation of the new bridge will be available on Website as soon as the work is completed. | |||||||
|
15th May 2002: Information Source, DNT Technical Committee Chairman. | |||||||
|
We got a grant of £17,000 less 11% from WREN. I have applied to the Horace
Taylor Trust as well, but no response till end of month. | |||||||
| IWA Grant Towards Brigham Bridge Click HERE | |||||||
|
With the swing bridge in place at Brigham and the
completion of Snakeholme lock restoration in 2002, next years Canal
Gala could be held at WANSFORD. | |||||||
|
|
|||||||
|
|
|||||||
| Pictures of Brigham Bridge as it was | |||||||
|
|
||||||
| Below picture of the new bridge taken on 29th June 2002 | |||||||
|
|||||||
| For the installation of the bridge, pictures and Video Click Here | |||||||
|
Pictures below taken on 6th July 2002. The bridge main structure weighs 7 tons and each of the five deck plates weigh 1.5 tons. Giving the bridge a total weight of 14.5 tons. (built to Motorway standards). |
|||||||
|
|
||||||
|
The area adjacent to the bridge has been cleared ready for the bridge to swing (once the bearing has been fitted). |
Looking across the bridge towards Brigham. Work is still required to replace brick work and tidy up the approaches to the bridge. |
||||||
|
HOME PAGE - Feasibility Study - Some History - Distance Table - Accommodation - SITE MAP - Links |
|
Gallery The Locks - Gallery Places - Gallery Scenery & Misc. - Gallery The Past |